Loading...

City of Troy

500 West Big Beaver
Troy, MI 48084
Ph: 248.524.3300

Troy Roads Rock

Concrete Slab Replacement: Todd, Big Beaver to Butterfield
All dates are weather dependent - schedule is subject to change
 
Tentative Schedule

9/13: Concrete removal will begin on the west side of Todd.
9/26: The contractor is working to pump water out of open holes so they can continue pouring concrete.
10/1: Due to the heavy rain we are experiencing we will be expecting delays in the schedule. Once the weather clears up the contractor will flip traffic and start removals on the east side of Todd.
10/8 & 10/9: Traffic will be flipped and removals will begin on the east side of Todd.
10/11: The contractor will continue to remove concrete on the east side of Todd.
10/16: The contractor has finished pouring concrete. Todd will be re-opened to traffic next week.

Detour: For the duration of this project only southbound Todd traffic will be permitted. Northbound Todd traffic is advised to use the following posted detour: SB Todd > Butterfield > EB Big Beaver > SB Todd.
Detour Map

Expected completion: End of October 2018.


Concrete Slab Replacement: Axtell Dr., Somerset to Maple
All dates are weather dependent - schedule is subject to change
 
Tentative Schedule

9/13: Asphalt milling will begin on Axtell. This is a rolling operation with no closures or detours.
9/14: Removal of concrete will begin. Beginning Friday only northbound Axtell traffic will be permitted. See detour information below.
Week of September 17th: The contractor has begun removing concrete. Due to rain this operation has been delayed but will pick back up on Friday.
9/26: The contractor is working to pump water out of open holes so they can continue pouring concrete.
10/3: Concrete on Axtell will be poured beginning Thursday 10/4
10/8: The contractor will continue to pour concrete on Axtell, weather permitting.
10/12: The contractor will be flipping traffic to the begin removing concrete on the other side of Axtell.  The detour will remain the same.
10/15: The contractor is working to form and grade the area to prepare to pour concrete this week.
10/16: The contractor will begin pouring concrete on Axtell. Pouring is expected to be completed by Wednesday 10/18 (excluding gaps).
10/18: The contractor was finished pouring the main line on Axtell. Once this has cured the contractor will work to fill in open areas (gaps).


Detour: For the duration of this project only northbound Axtell traffic will be permitted. Southbound Axtell traffic is advised to follow the posted detour: NB Axtell > WB Somerset > SB Coolidge > MI left to NB Coolidge > EB Maple > NB Axtell
Detour Map

Access to some parking lot entrances will be temporarily closed or shifted during this project. Please see the map below for more information.
Driveway Closure Map

Expected completion: End of October 2018.



Concrete Slab Replacement: Rochester Road
All dates are weather dependent - schedule is subject to change
 
Tentative Schedule
10/23 (Tuesday)
:
The contractor will be removing various slabs of concrete on Rochester Rd just north of Long Lake. Only one lane of traffic will be permitted during this time. The contractor will also be removing a small area on SB Rochester, just south of Lovell. One lane of traffic will be permitted SB during this time as well.

The contractor will be removing and pouring concrete on the same day to minimize closures and traffic as much as possible. Rochester Rd will be fully re-opened by Monday, October 29th.

 

Concrete Slab Replacement: Local Subdivision Roads
All dates are weather dependent - schedule is subject to change 
Please see FAQ page (linked below) for information regarding slab replacement projects.

 Click the street name below for a map showing construction areas. Areas of the road that will be removed are in blue. Notices with a start date have been delivered to houses within the construction area. If your driveway will be blocked during this project, please make arrangements to move vehicles from driveways.  More information on the slab replacement process can be found below on our FAQ document.


Mountain @ Pinoak             
- 10/18: The contractor has poured concrete on the second phase. These areas are curing and will be re-opened next week.

Crestview                                 
- 10/18: The contractor has poured concrete on the second phase. These areas are curing and will be re-opened next week.

Russet @ Johnathon          
- 10/19: The contractor is expecting to begin pouring concrete today.

Tanglewood/Shagbark/Red Maple/Red Oak/Parkview
- 10/19: The contractor is expecting to begin pouring concrete today and will continue on 10/22.

Fleetwood
- 10/18: The contractor has removed concrete in the first phase. They will work to form and grade the open areas to prepare to pour concrete next week.

Lockmoor @ Stonehaven
- 10/19: The contractor began removing concrete on 10/18. Due to an issue with equipment they were unable to finish. The contractor is expected to finish today.

Roxbury @ Cedar Ridge and Dartmoor
- 10/18: The contractor has begun removing concrete. Once they are completed they will work to form and grade the open areas to prepare to pour concrete.

Lila
- Removal of concrete is scheduled to begin Friday, 10/19.

Westpointe
- Removal of concrete is scheduled to begin Friday, 10/19.

Coral & Willard
- Removal of concrete is scheduled to begin Friday, 10/19.

Fedora
- Removal of concrete is scheduled to begin Friday, 10/19.

Carr - Hubbard - Calvert
- Removal of concrete is scheduled for Friday 10/19 and Monday 10/22.

Brahms
- Removal of concrete is scheduled for Friday 10/19 and Monday 10/22.

Horseshoe
- Removal of concrete is scheduled for Friday 10/19 and Monday 10/22.

Acorn
- Removal of concrete is scheduled for Friday 10/19 and Monday 10/22.

Otter & Cedar Knoll
- Removal of concrete is scheduled for Friday 10/19 and Monday 10/22.

Parasol
- Removal of concrete is scheduled for Friday 10/19 and Monday 10/22. This will likely occur Monday.

Milverton @ Gulason
- Removal of concrete is scheduled for Friday 10/19 and Monday 10/22. This will likely occur Monday.



 Questions? Check out our FAQ or Contact Us!

Department of Public Works
4693 Rochester Road Troy, MI 48085
248.524.3392
Email

icon
CITY UPDATES