Loading...

City of Troy

500 West Big Beaver
Troy, MI 48084
Ph: 248.524.3300

Construction Updates


Road Commission for Oakland County Construction Updates

John R Widening , Long Lake to South Blvd.

Dequindre Reconstruction, Long Lake to Beaumont Hospital

QUARTERLY CONSTRUCTION PROJECTS
August 2018 - November 2018

1. MAJOR ROAD WIDENING AND RECONSTRUCTION – DEQUINDRE, LONG LAKE TO BEAUMONT HOSPITAL
Dequindre is being widened and reconstructed to a new 5-lane concrete roadway between Long Lake and Beaumont Hospital.  All road work is to be complete and open to traffic by late fall 2018.

2. ROAD WIDENING AND RECONSTRUCTION – JOHN R, LONG LAKE TO SOUTH BOULEVARD
John R will be widened and reconstructed to a new 3-lane asphalt pavement with deceleration lanes at side streets between Long Lake and South Boulevard.  Construction is anticipated to start in late fall 2018 with the underground portion of the project.  Paving will start in the spring of 2019.  Detours are anticipated for through traffic during the paving phase.  All road work is anticipated to be complete and open to traffic by late fall of 2019.

3. MAJOR ROAD REHABILITATION – SOUTH BOULEVARD, ADAMS TO COOLIDGE
This project will remove and replace the pavement between Adams and Coolidge.  Detours are anticipated for through traffic.  Work has started and is anticipated to be complete by September.

4. MAJOR ROAD REHABILITATION - ADAMS, SQUARE LAKE TO SOUTH BOULEVARD
The project will mill (grind off) the pavement surface between Square Lake and South Boulevard and overlay it with asphalt pavement.  Detours are anticipated for through traffic.  Work is anticipated to start in late July and be complete by November.

5. MAJOR ROAD REHABILITATION – LIVERNOIS, MAPLE TO BIG BEAVER
The project will mill (grind off) the pavement surface between Maple and Big Beaver and overlay it with asphalt pavement.  Work is anticipated to start in August and be complete by November.

6. MAJOR ROAD CONCRETE PAVEMENT REPLACEMENT – LONG LAKE, CORPORATE TO TOWER
Select areas of concrete pavement will be removed and replaced on Long Lake, between Corporate and Tower.  Work started in June and is anticipated to be complete by August.

7. MAJOR ROAD CONCRETE PAVEMENT REPLACEMENTCOOLIDGE, MAPLE TO SOUTH CITY LIMITS
Select areas of concrete pavement will be removed and replaced on Coolidge, south of Maple.  Work is anticipated to start in late summer and be complete by November.

8. INDUSTRIAL ROAD CONCRETE ROAD REPLACEMENT – NORTHFIELD PARKWAY, LONG LAKE TO BREEZE HILL
Northfield Parkway, from Long Lake to Breeze Hill will be removed and replaced with new concrete Pavement.  This work will be done under a full closure, so a detour will be established.  Work is anticipated to start in August and be complete before school starts.

9. INDUSTRIAL ROAD CONCRETE ROAD REPLACEMENT – TODD DRIVE, BUTTERFIELD TO BIG BEAVER
Todd Drive, from Butterfield to Big Beaver will be removed and replaced with new concrete pavement.  Select areas of concrete pavement will be removed on Butterfield, from Crooks to Big Beaver.  No full closures are anticipated.  Work is anticipated to start in late summer and be complete by November.

10. LOCAL ROAD OVERLAY – MT. VERNON ESTATES – SECTION 13
The project will mill (grind off) the pavement surface and overlay it with asphalt pavement.  Overlay work is anticipated to begin in August and be complete by October.

11. LOCAL ROAD OVERLAY – SECTION 14
The project will mill (grind off) the pavement surface and overlay it with asphalt pavement.  Work is anticipated to start in July and be complete by September.

12. WATER MAIN REPLACEMENT - ROUNDTREE LOOP
The water main portion of the project was completed in July.  Roadwork and restoration is anticipated to be complete by September.

13. WATER MAIN REPLACEMENT – ROAD CROSSINGS ON CROOKS AND COOLIDGE
Several water main road crossings will be replaced with new water main.  The locations are: Crooks, Between Maplelawn and Kirts; and Coolidge, between Mountain and South Boulevard.  Work is ongoing and anticipated to be complete by September.

14. CULVERT REPLACEMENT – FERRY DRAIN – SOUTH BOULEVARD, ROCHESTER TO JOHN R
South Boulevard will be closed between Rochester and John R to facilitate the removal and Replacement of the large diameter culvert carrying the Ferry Drain under South Boulevard.  Detours are anticipated for through traffic.  Work is anticipated to start in October and be complete by mid-November.

***LOCAL ROAD CONCRETE PAVEMENT REPLACEMENT
The Department of Public Works (DPW) will be replacing concrete pavement at scattered locations throughout the City.  Specific locations are not shown on the map.  Additional information is available at: www.troymi.gov/streetsprojects.  

 

icon
CITY UPDATES